Purpose


Apparel Capacity Planning

Admin Info


Purpose
Apparel Capacity Planning
Requested By
Josh Creasman
Spec Created By
Damodhier/Laxman
Spec Created Date
04/19/2016
Spec QA by
Damodhier
Objects
ZMMENGG_MAT
Document Status
Completed


Estimates



Sl.No
Activity
Estimation in Hours
1
Research
02
2
Documentation
02
3
Development/ Config
06
4
Unit test in DEV
02
5
Unit test in QUA
02
6
Other activity


TOTAL
14

References


Prior Tickets

[Provide links of prior associated Spec / Break Fix BOSS document(s)]



Documents

[Attach any document(s) received for the requirement(s)]
1Untitled.png

Spec Changes


[List the changes made to program after the approval of the original requirement along with the Date on which the change request was received and the name of the initiator]

Sl.
Change Details
Requested By
Requested On
Notes if any

























Functional Requirement


Purpose/WHY:

[Explain the purpose of the project and the reason why this requirement has come]

Due to change in the 1410 production process advised to change the labor time in the Routing.

In Scope:

[List the activities to be included in scope]

Applicable only to apparel materials which are created using Engineering program

Out of Scope:

[Out of scope activities]
Material creation Other than the Engineering Program

Solution Summary


[Discuss this section with Requester and get approval prior to beginning work]

To change the labor time in the routing need to change corresponding LSMW. Details are give below.

LSMW - ENGINEERING - PR-ROUTING - CAPMACHINE

Test Plan

[List test scenarios/cases to be executed here]
Test ID
Test Scenario
Expected Results
MM001
Create the material and routing in plant 1410
In the routing for operation 20 labor time should be 5.64 MINS
In the routing for operation 30 labor time should be 1.60 MINS

Solution Details


[Provide complete technical details for configuration or programming here]

Modified LSMW (ENGINEERING - PR-ROUTING - CAPMACHINE) to set labor time 5.640 Mins for Activity Type 'MI100', 1.600 Mins for Activity Type 'MI400'
Given support to modify the existing routings and to update the corresponding planned orders and production orders.



Issues